𝐌𝐚𝐯𝐢𝐬𝐭𝐨𝐧 𝐂𝐨𝐧𝐬𝐭𝐫𝐮𝐜𝐭𝐢𝐨𝐧 𝐏𝐫𝐨𝐠𝐫𝐞𝐬𝐬 𝐔𝐩𝐝𝐚𝐭𝐞 –𝐉𝐮𝐥𝐲 𝟐𝟎𝟐𝟔

We’re making steady progress across every building at Maviston Resort & Spa, with construction advancing according to plan.

Building J1

• Structural Construction: 90% Complete

• Architectural Works: 81% Complete

• MEP (Mechanical, Electrical & Plumbing): 86% Complete

Building J2

• Structural Construction: 90% Complete

• Architectural Works: 70% Complete

• MEP: 80% Complete

Building K1

• Structural Construction (excluding swimming pool): 65% Complete

• Architectural Works: 10% Complete

• MEP: 35% Complete

Building K2

• Structural Construction: 78% Complete

• Architectural Works: 60% Complete

• MEP: 68% Complete

Building K3

• Structural Construction: 81% Complete

• Architectural Works: 32% Complete

• MEP: 65% Complete

Every milestone reflects the dedication and hard work of our teams and partners. We remain fully committed to maintaining the highest standards of quality while keeping the project on schedule.

We are doing our very best to deliver Maviston Mai Khao Resort & Spa on time and look forward to welcoming you to an exceptional beachfront experience soon. Stay tuned for more construction updates as we continue bringing our vision to life.