We’re making steady progress across every building at Maviston Resort & Spa, with construction advancing according to plan.

Building J1
• Structural Construction: 90% Complete
• Architectural Works: 81% Complete
• MEP (Mechanical, Electrical & Plumbing): 86% Complete
Building J2
• Structural Construction: 90% Complete
• Architectural Works: 70% Complete
• MEP: 80% Complete
Building K1
• Structural Construction (excluding swimming pool): 65% Complete
• Architectural Works: 10% Complete
• MEP: 35% Complete
Building K2
• Structural Construction: 78% Complete
• Architectural Works: 60% Complete
• MEP: 68% Complete
Building K3
• Structural Construction: 81% Complete
• Architectural Works: 32% Complete
• MEP: 65% Complete



Every milestone reflects the dedication and hard work of our teams and partners. We remain fully committed to maintaining the highest standards of quality while keeping the project on schedule.
We are doing our very best to deliver Maviston Mai Khao Resort & Spa on time and look forward to welcoming you to an exceptional beachfront experience soon. Stay tuned for more construction updates as we continue bringing our vision to life.