Maviston Construction Progress Update – October 2025
We are pleased to share with you the latest update on the progress of Maviston Mai Khao, developed by Mai Khao Golden Beach. Our team is working step by step to bring the project closer to completion, and we are delighted to keep you informed along the way.

Building J1
- Structural construction (excluding swimming pool): nearing completion
- Architectural work: 60% completed
- MEP (Mechanical, Electrical & Plumbing): 55% completed
Building J2
- Structural construction (excluding swimming pool): nearing completion
- Architectural work: In progress (installation phase)
- MEP: 40% completed
Every completed stage brings us one step closer to welcoming you to the Maviston Mai Khao experience.
We remain committed to delivering exceptional quality and maintaining steady progress throughout the construction process Stay tuned for our next update — 𝐲𝐨𝐮𝐫 𝐛𝐞𝐚𝐜𝐡𝐟𝐫𝐨𝐧𝐭 𝐞𝐬𝐜𝐚𝐩𝐞 𝐢𝐬 𝐨𝐧 𝐭𝐡𝐞 𝐡𝐨𝐫𝐢𝐳𝐨𝐧.