Maviston Construction Progress Update – SEPTEMBER 2026

We are pleased to share the latest construction progress at Maviston Mai Khao for September 2026.

Construction continues to advance across all buildings, with structural, architectural, and MEP works progressing simultaneously. Our team continues to closely monitor each stage of construction and coordinate with the relevant contractors to maintain quality, safety, and overall project progress.

Building J1
  • Structural Construction: 95% Complete
  • Architectural Works: 81% Complete
  • MEP (Mechanical, Electrical & Plumbing): 86% Complete

Building J2

  • Structural Construction: 95% Complete
  • Architectural Works: 70% Complete
  • MEP: 80% Complete
Building K1
  • Structural Construction: 75% Complete
  • Architectural Works: 30% Complete
  • MEP: 52% Complete
Building K2
  • Structural Construction: 90% Complete
  • Architectural Works: 65% Complete
  • MEP: 68% Complete
Building K3
  • Structural Construction: 90% Complete
  • Architectural Works: 55% Complete
  • MEP: 68% Complete

We sincerely appreciate your continued trust and support as Maviston Mai Khao takes shape. We look forward to sharing further progress updates as we move closer to completion.