Construction at Maviston Resort & Spa continues to progress across all buildings, with steady advancement in structural, architectural, and MEP works. While the project remains actively progressing, certain activities and timelines are being carefully reviewed and adjusted to ensure the overall quality and coordination of the development.



Building J1
• Structural Construction: 95% Complete
• Architectural Works: 81% Complete
• MEP (Mechanical, Electrical & Plumbing): 86% Complete
Building J2
• Structural Construction: 95% Complete
• Architectural Works: 70% Complete
• MEP: 80% Complete
Building K1
• Structural Construction (excluding swimming pool): 74% Complete
• Architectural Works: 10% Complete
• MEP: 48% Complete
Building K2
• Structural Construction: 89% Complete
• Architectural Works: 60% Complete
• MEP: 68% Complete
Building K3
• Structural Construction: 90% Complete
• Architectural Works: 40% Complete
• MEP: 68% Complete
Our team remains fully committed to the project and will continue to closely monitor and adjust the construction schedule as needed, while maintaining the quality and standards of Maviston Resort & Spa.