Maviston Construction Progress Update – June 2026


• Structural construction : 87% completed
• Architectural works: 78% completed
• MEP (Mechanical, Electrical & Plumbing): 85% completed
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐉𝟐
• Structural construction 90% completion
• Architectural works: 70% completed
• MEP: 70% completed
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐊𝟏
• Structural construction (excluding swimming pool): 60% completed
• Architectural works: 10% completed
• MEP: 20% completed
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐊𝟐
• Structural construction 78% completed
• MEP: 68% completed
• Architectural works: 50% completed
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐊𝟑
• Structural construction 81% completed
• MEP: 65% completed
• Architectural works: 30% completed
As of June 2026, construction continues to advance according to schedule, with significant progress achieved across the development. Our team remains dedicated to maintaining exceptional quality standards while ensuring efficient project execution. We look forward to providing you with further updates next month as Maviston continues to take shape along Mai Khao Beach.