Maviston Construction Progress Update – January 2026
We are pleased to share with you the latest update on the progress of Maviston Mai Khao, developed by Mai Khao Golden Beach. Our team is working step by step to bring the project closer to completion, and we are delighted to keep you informed along the way.




𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐉𝟏
* Structural construction (excluding swimming pool): nearing completion
* Architectural work: 65% completed
* MEP (Mechanical, Electrical & Plumbing): 65% completed
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐉𝟐
* Structural construction (excluding swimming pool): nearing completion
* Architectural work: 38% completed
* MEP: 60% completed
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐊𝟏
* Structural construction (excluding swimming pool): 15%
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐊𝟐
* Structural construction (excluding swimming pool): 50%
* MEP: 15% completed
* Structural construction (excluding swimming pool): 50%
* MEP: 15% completed
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐊𝟑
* Structural construction (excluding swimming pool): 80%
* MEP: 28% completed
Every completed stage brings us one step closer to welcoming you to the Maviston Mai Khao experience. We remain committed to delivering exceptional quality and maintaining steady progress throughout the construction process
Stay tuned for our next update